Progress is visible every week at the construction meetings held on Wednesday morning. The concrete half wall around the pool has been completed. The drainage system around the pool has been completed. The pool systems and pumps was tested successfully before completion of concrete work. The floor around the pool is being prepared for the pouring of the stamped concrete. The inspections for framing and electrical have been signed off. The insulation will begin on Thursday and dry walling on Friday. Structural cracks in the concrete at the front entrance are continuing to be worked on with the delivery of the steel beams for reinforcement.